Anoka Conservation District, in partnership with Anoka County Parks, received a MNDNR behavior change grant in the amount of $4,992.74 to pilot a strategy to reduce the spread of aquatic invasive species. The pilot behavior change intervention strategy will be delivered to the target audience of boaters and anglers through the installation of new boat cleaning equipment at 5 high traffic boat launches and education provided by on-site AIS inspectors. The project will influence positive behavior change in boaters and anglers by removing barriers such as lack of access to tools/equipment for properly cleaning boats/trailers, lack of space to clean boat or pressure caused by high-traffic boat launches, and lack of knowledge of how to use cleaning tools/equipment. We will lay the groundwork by conducting research on baseline boater behavior this summer, install the weed removal stations in spring of 2021, and collect observational data on weed removal station use and commitments to use the stations from boaters throughout the 2021 boating season. The results of the pilot study will be used by the DNR in future AIS behavior change strategies throughout the state.

  2111 Hits

Rum River Central Regional Park Riverbank Stabilization

The Anoka Conservation District partnered with Anoka County Parks to stabilize 310' of eroding riverbank within Rum River Central Regional Park. Prior to the project, the bank was severely eroding and undermining sections of a paved trail. The stabilization project is now complete and included the following elements:

  • Minimal riprap at the bottom of the slope within the zone of frequent water level fluctuation where vegetation does not grow well,
  • Grading above the riprap to the top of the slope (3H:1V), seeding with native vegetation, and installation of an erosion control blanket,
  • Relocation of the paved trail to ensure sufficient separation between the trail and the new top of slope, and
  • Dormant willow stakes were installed in November 2019 as the final phase of the project.

Stabilization of the bank will prevent 100 tons of sediment annually from entering the Rum River. Multiple State and local funding sources were used to complete the project.