SONAR AS A DESIGN TOOL FOR SHORELINE STABILIZATION PROJECTS

Data collection on the Rum River.

ACD staff have been testing the use of sonar to aid with the design of shoreline stabilization projects.

Lake and river bottom elevations are often required when designing projects. Collecting these bottom elevations manually with survey equipment often pose safety risks, limits resolution, and can be time consuming. Automated collection of underwater elevation data is possible with readily available sonar technology and post-processing services. Manually collecting data at the same resolution is infeasible.

A fishing depth finder and transducer combination with active mapping capabilities is necessary for data collection. The equipment can be configured in a portable setup for use in a kayak, canoe, or motorized boat to enable data collection on a variety of waterbodies (e.g. stormwater ponds, lakes, or the Mississippi River). While idling or paddling around the area of interest, data is collected and stored on a memory card and then uploaded to a third-party software for post-processing.

Technology limitations still remain, but the end products provide a picture of the underwater landscape through a variety of file types that are useful for project design, mapping, and inventory work. 

For more information contact Mitch Haustein at 763.434.2030 ext. 150 or This email address is being protected from spambots. You need JavaScript enabled to view it..

  810 Hits
Tags:

Rum River Central Regional Park Riverbank Stabilization

The Anoka Conservation District partnered with Anoka County Parks to stabilize 310' of eroding riverbank within Rum River Central Regional Park. Prior to the project, the bank was severely eroding and undermining sections of a paved trail. The stabilization project is now complete and included the following elements:

  • Minimal riprap at the bottom of the slope within the zone of frequent water level fluctuation where vegetation does not grow well,
  • Grading above the riprap to the top of the slope (3H:1V), seeding with native vegetation, and installation of an erosion control blanket,
  • Relocation of the paved trail to ensure sufficient separation between the trail and the new top of slope, and
  • Dormant willow stakes were installed in November 2019 as the final phase of the project.

Stabilization of the bank will prevent 100 tons of sediment annually from entering the Rum River. Multiple State and local funding sources were used to complete the project.

  2532 Hits