Project Update: Apex Pond Enhancement

September, 2023 - De-watering of Current Pond, Tree Removal  
October, 2023 - Water Storage Capacity Increased, Plantings to Come

Construction of the Apex Pond enhancement project in the City of Fridley is nearly complete (see pictures above). The only remaining elements are to spread native seed and lay erosion control blanket over the upper slopes surrounding the pond. Apex Pond in the City of Fridley was originally constructed in 1999 to help control the rate of stormwater runoff entering Springbrook Creek from nearly 90 acres of residential neighborhoods. ACD, in partnership with the City of Fridley and the Coon Creek Watershed District (CCWD) identified an opportunity to enhance the water quality treatment capacity of Apex Pond by increasing the pond's storage volume.

You can also check for project updates on the City of Fridley's website: https://www.fridleymn.gov/1655/Apex-Pond-Enhancement-Project.

For more information contact Mitch Haustein, Stormwater and Shoreland Specialist, at This email address is being protected from spambots. You need JavaScript enabled to view it..

  973 Hits

Stormwater Pond Enhancement - Construction Begins Soon

Apex Pond in the City of Fridley was originally constructed in 1999 to help control the rate of stormwater runoff entering Springbrook Creek from nearly 90 acres of residential neighborhoods. ACD, in partnership with the City of Fridley and Coon Creek Watershed District (CCWD) identified an opportunity to enhance the water quality treatment capacity of Apex Pond by increasing the pond's storage volume.

Project construction will consist of two phases: 1) maintain the pond by removing accumulated sediment and undesirable vegetation to restore original function, and 2) enhance the pond by increasing the depth to approximately six feet. Mature trees around the pond will be preserved where possible and native vegetation will be used to restore the pond side slopes. A vegetated, level bench will also be incorporated around the perimeter of the pond to provide habitat value and increase safety.

Both Springbrook Creek (County Ditch #17) and the Mississippi River will benefit from the project as the pond outlets to Springbrook, and Springbrook is a tributary to the Mississippi. Total annual reductions to Springbrook and the Mississippi River include 16.80 lbs-TP/yr and 6,617 lbs-TSS/yr. Construction is tentatively scheduled to begin in early October.

Pond maintenance will be funded by the City of Fridley, and pond enhancement will be funded with a combination of Watershed Based Implementation Funds from the Board of Water and Soil Resources, a CCWD Water Quality Cost-Share Program grant, and the City of Fridley.

You can also check for project updates on the City of Fridley's website: https://www.fridleymn.gov/1655/Apex-Pond-Enhancement-Project 

  623 Hits

What is an As-Built, and Why is it Important?

ACD recently led a project that improved the water quality benefits provided by two stormwater ponds adjacent to Martin Lake in Linwood Township. The project increased the size and depth of the ponds to the maximum extent practicable within the limited spaces available. The projects were a great success, and were recently highlighted in an outreach article titled, 'Water Quality Improvements Constructed for Coon and Martin Lakes'. They're worth mentioning again in order to highlight a critical piece of successful construction management that most people never see, the as-built survey.

As-built surveys, also commonly referred to as record drawings, provide formal documentation of exactly how a project was installed. They document the actual results of the construction project rather than the planned layout shown in the project design and are critical for project closeout.

As-built surveys ensure the project was built to meet the specifications in the original plan set. This allows the project engineer to confidently sign-off that the project was installed as per the plan. If any deviations from the original plan were approved during the construction process, the as-built survey will show the changes as they were installed and provide an opportunity to formally document those changes. Final payment to the contractor is also typically withheld until engineer sign-off on the as-built survey.

The as-built survey also provides a formal record that can be used to standardize how a project should be maintained over its lifespan. In the event of these stormwater ponds, accumulated sediment and debris should be periodically removed to achieve the original design depths in order to ensure the ponds continue to function at maximum efficacy.

Depending on the type and scale of a project, multiple as-built surveys may be completed throughout the construction process to confirm critical elevations and layouts are being met prior to approving advancement to the next construction step. They are typically shown as an overlay on the original plan sheet to allow a direct comparison and easy identification of any significant deviations from the original plan.

The 228th Place stormwater pond as-built (see plan sheet below) documented key elevations around the pond to ensure safe side slopes were achieved. It also documented the stabilized outlet and controlled overflow elevation to ensure neighboring properties were not at risk of flooding as a result of the project.

As-built surveys and the associated formal documentation they provide can sometimes be neglected because project installation went smoothly and according to plan, but they are a critical component to successful construction management and project closeout.

  12519 Hits

Water Quality Improvements Constructed for Coon and Martin Lakes

One rain garden and two stormwater pond renovations were completed in November to treat stormwater before it reaches Martin and Coon Lakes. The projects will collectively treat 39 acres of residential development that previously were draining to the lakes with little or no treatment. They will keep 2,100 pounds of sediment and 5 pounds of phosphorus from reaching the lakes each year.

These waterbodies were priorities because both lakes are surrounded by homes and heavily used for recreation. Martin Lake is nearing the criteria for being removed from the State's list of impaired waters. Coon Lake has good water quality but is under pressure.

The rain garden was constructed in cooperation with a residential landowner along Hupp Street. Their property is a key location where drainage from 8 acres converged and entered a catch basin that piped stormwater to Coon Lake. Curb cuts on each side of the catch basin now intercept that water, allowing it to soak into the ground within the rain garden. Pollutant removal is estimated to increase by 52% compared to the pre-project condition. Mulching and planting of the gardens will be delayed until spring 2021 due to cold temperatures early in fall 2020. The property owners will maintain the garden.

The stormwater pond projects are redesigns and renovations of older ponds. Both ponds are on Martin Lakeshore within township-owned property. Both basins had filled with sediment over time and were providing little water quality treatment. Now, the basins are even larger than originally constructed to maximize pollutant removal. Pollutant removal is estimated to increase by 84% and 104%, respectively, at the two ponds. Linwood Township will own and maintain the basins.

These projects are part of a State Clean Water, Land and Legacy grant to the Sunrise River Watershed Management Organization. The Anoka Conservation District is managing the projects. Additional funds remain and will be used for similar projects in 2021.

Collaborators on these projects included the ACD, SRWMO, Martin Lakers Association, Linwood Township, and the City of East Bethel.